Primavera enterprise

Mohamed NizamMember for 19 years 7 months
Created
3
1
0


In Primavera Enterprise Project Management Module > Project> WBS

Now for example –build1234
Build1234.2
Build1234.1
Build1234.3
Build1234.5
Build1234.4

Now To arrange like Build1234.1
Build1234.2
Build1234.3
Build1234.4
Build1234.5

I made Projects>Activites
Then View > Group and sort > WBS level
Then sort >WBS then apply

Result : failure i.e not ordered as I wished
Can anyone suggest solution

3 replies

Oldest first
  1. 0
    James Shimmon ·
    just use the sort function in the WBS view and move your WBS levels to were you want them using the indent buttons
  2. 0
    Mohamed Nizam ·
    not satisfied . The one Mr. james told is already I tried but failed. I need a brief detail which somebody faced like this problem and then got solution
  3. 0
    Jorge Taguinod ·
    This one’s very easy.

    Go to WBS Windows
    Arrange your WBS nodes by using the Up,Down,Left,Right arrows.
    Go back to Activities
    Organize by WBS (indent, all levels)
    Do not check the last box on the lower left of the Orgnize screen (which says something about alphabetically sorting your titles).

    You will see the WBS properly arranged.

    Jorge