p5 to p3 conversion date problem

Kier LegardMember for 20 years 2 months
Created
2
3
0

I have a project which was created in p5 but when i convert it to p3 the dates are 1 day ahead compared to p5 .what seems to be the problem?

Our client is using p3 but our company now is using p5



regards,
kier

2 replies

Oldest first
  1. 0
    Benjamin Mora ·
    After a lot of discussion with the vendor, the conversion is not always going to be perfect. Allegedly, there things that you can do to the P5 schedule to make the backward conversion better, but I have never seen it done. I think your calendar(s) is this issue.
  2. 0
    Johny Kesserwany ·

    P5 is using the HOUR as basis of calculation, when P3 is using the DAY !
    AS Benjamin said there is not a solution for that. Primavera promized to solve the issue later on as an enhansment request to P6 from the Construction industry !!!
    We are still waiting..
    Regards