Scheduled % complete v/s Activity % complete curve

Abhijit SuvarnaMember for 18 years 7 months
Created
4
1
0
could anyone guide me in generating a curve showing the scheduled% v/s activty complete%
regards

4 replies

Oldest first
  1. 0
    Niles Luo ·
    Hi:
    Pls give the further information about:
    1,Do you want to show the S curve in PM or the other system just like MS Excel?
    2,Do you assign resources to the activities?
  2. 0
    Abhijit Suvarna ·
    I want to show the S curve in PM & I have not yet assigned resources
  3. 0
    Niles Luo ·
    Hi,
    I think in this situation PM can not direct show this S curve.Maybe PM can,but I do not know.
    My suggestion is
    1,Create a resource named A, labor or nonlabor is ok
    2,Assign resource A to every activity. The Unit use the default value is ok.
    3,Then use the Resource Usage Profile, we can see the Unit Cumulative Curve of resource A. The numuber/total unit is the percent complete.
    Maybe above is not a good idea, only FYI.
  4. 0
    Abdullah Merchant ·

    Hi, I am relatively new to

    Hi,

    I am relatively new to planning, and I am currently working on a Project(Clients Side) where I have not loaded any resources. I am currently using MS Project 2007 adn would like to know how to get and S Curve in excell.

    Also, I have notice that the baseline dates in MS Project can be chnaged from the column,unlike P6. Is this so or am i missing something here.

Log in or join to reply