IMPORTING FROM P3E 3.5.1 TO P5

Suresh Sankarankutty PMPMember for 20 years 2 months
Created
5
1
0
Hi
Have you ever faced this problem ?
I am not able to import the p3e 3.5.1 file in p5 . It says can not import files from version 3.5.1.

The long way i done is imported the file in p4 and exported again and imported in p5 .


Is ther any otherways or reasons / solutions ?

Suresh

5 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Suresh
    Some time ago I had to import 2.1-files into P5. It worked with a small trick.
    Primavera by default only allows to import from the previous version. 2 things to be done:
    1. The information by which version the xer was produced is in the first line. You’ll modify 3.5 to 5.x - your version.
    2. Check if a group name was modified. I don’t believe this is the case. If yes you’ll change it to the new name.
    (In the bove mentioned case I had to do it.)
    You can open a xer-file with any editor.
    Regards
    Dieter
  2. 0
    Suresh Sankarankutty PMP ·
    Hi Dieter
    Could you pls explain me on which editor we can open the xer file. Do you mean like MS Word or something ?
    Pls explain in more detail.
    thnx
    Suresh
  3. 0
    David Forrest ·
    XER can be opened with Notepad. This is useful for doing quick integrity check prior to importing projects from other databases.
  4. 0
    Dieter Wambach ·
    Hi Suresh
    It must be a normal Editor: Notepad (--> see David’s post), Editor, or Wordpad. Never use a wordprocessing software (Word, Open Office, WordPro...), because this will add many control blocks, formatting and others. The XER-file would be destroyed.
    Only work with a copy!
    Regards
    Dieter
  5. 0
    Suresh Sankarankutty PMP ·
    Dieter ,
    Lovely solution. I tried and working perfect.
    Thanks a lot...
    Regards
    Suresh

Log in or join to reply