P5 Variance in Summary level ---Original Duration

Jiso ThomasMember for 18 years 7 months
Created
3
1
0
Hai Friends,

I am a new user in P5 & we are using different calendar (7days/week calendar and 6days/week).My default calendar in enterprise level is 7days/week.Now the issue is when i am summarizing in activity code level, original duration is shown according to Default 7days/week calendar. But i assigned 6days/week calendar for all activities under that particular activity code level.

Can anybody explore and resolve this?

Thanks,

Jiso

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Jiso
    As activities in Primavera can have different calendars, durations show in the summary bars by default are assigned to the default calendar.
    If you’ll study PP you’ll find quite a few threads on this topic.
    Regards
    Dieter
  2. 0
    Andrew Dick ·
    Jiso,

    If you follow this thread and study the other 2 that it references then you will see some of the frustrations we come across with this subject.


    Primavera Duration Threads

    Andy
  3. 0
    Jiso Thomas ·
    Thanks Guys,

    I understood that this is a unsolved problem where we are using more than one calender in a project,Otherwise we need to switch in to WBS summary level.

    Thanks for quick response & cooperation.

    Regards,

    Jiso