Resource Distribution- Anomalise
In the Open Standard
Jiso ThomasMember for 18 years 7 months
- Created
- 7
- 4
0
Hai Friends,
Onother issue.We are loading more resources in one activity.But in reality both resources will not start cuncurrently.
Example,
Pipe fitter will start first after 3 days welder will start welding.But when i am taking the spread both will start at the same time.
In my organization, we are using craftwise table for comparing actual and planned figures in management meeting.
In the start up stage of piping and structural activities i am getting unrealistic forcast at structul welder and pipe welder.In my netwok i have more than 50000 activities.
I think that now all of you have enough understanding about my issue.Please help me if you have any idea.
Onother issue.We are loading more resources in one activity.But in reality both resources will not start cuncurrently.
Example,
Pipe fitter will start first after 3 days welder will start welding.But when i am taking the spread both will start at the same time.
In my organization, we are using craftwise table for comparing actual and planned figures in management meeting.
In the start up stage of piping and structural activities i am getting unrealistic forcast at structul welder and pipe welder.In my netwok i have more than 50000 activities.
I think that now all of you have enough understanding about my issue.Please help me if you have any idea.
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?