yes, ANOTHER, S-Curve question...

S HardingMember for 18 years 6 months
Created
3
2
0
Greetings All,

I have read many posts already about S-Curves using the Late and Early dates. I can do this in P3 fairly easy, but for some reason I am having quite the trouble getting the desired results from P6. I have exhausted all the resources I know to do this and can not get the reults I want.. which is the early and late dates, in a weekly format, to get the traditional ’banana’ curve that a lot of you are accustomed to.

Thanks in advance...

3 replies

Oldest first
  1. 0
    David Kelly ·
    Hmmm,

    I think its easy...... Maybe I could email you a "print screen" and see if its what you want?
  2. 0
    S Harding ·
    That would be great. One more thing to clarify however; I am wanting to get the Early and Late dates for a curve in Excel. You can send me a PM if you like, or post here.

    THANK YOU!
  3. 0
    David Kelly ·
    There are two ways to get Remaining Early and Remaining Late units from P6 into Excel.

    The "supported" way is to use the report wizard - all reports created this way can be "saved" as .csv files which will be opened automatically by Excel.

    The "unsupported" way is to use the "Resource Asignments" view. With a bit of care the aggregations produced here can be copy/pasted into Excel. This shouldn’t work. There is no "data source" for windows to copy - but it does.....

Log in or join to reply