Manhrs Loading In P6

Praju SatishMember for 20 years 9 months
Created
2
1
0
Hi Guys

I am trying to resource load the activites with Manhrs ,but I dont want to change the original duration when i do that.I just want to show the Proejct manager that the planned duration for this activity is x and whatever the manhrs the estimator has estimated is y.How do i do that.

The problem now I am facing is for an activity which has 10 days duration primavera assumes 80 budgeted units when i said budgeted units per time is 8/d.if i increase the budgeted units the duration changes..

2 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Praju
    This will depend on the duration type.
    I assume, that your type is "Fixed duration and units". the a change of budgeted units won’t impact the duration, just units/time.
    Regards
    Dieter
  2. 0
    Praju Satish ·
    Yup i fixed that..Thanks for your help