Problem with cost loading in P6.1
In the Open Standard
Marsha PetersonMember for 22 years 7 months
- Created
- 10
- 3
0
Forgive me if this has been discussed to death already. I have a project that needs to be cost loaded per activity. Thinking I could use same approach in P6 as P3, (was I thinking?), I set up costs in the expense tab.
When my colleague then was updating that activity, I realized that manual computation was need to update the new % cost complete. I then dumped all activities out, and reloaded into the resource (non-labor)tab, using LUMPSUM as a resource.
My colleague then went about updating, and then, no matter how I’d set up the Activity type (always Resource dependent) and the duration type and the % complete type, I couldn’t get the resources to update.
The tech support person said that I couldn’t use money as a resource and update % to derive amounts (i.e. 58% complete activity shows 58% actual cost to date)
I sarcastically then asked tech support if I’d have to use a spreadsheet to compute actuals. They said that was a good idea (like I was seriour), but the software won’t figure out actual costs from activity % complete. Did I misunderstand? Did I talk to the wrong person?
The "costs" in this case are an earned value that is really a cost to the owner, the amount we can bill for that much progress.
When my colleague then was updating that activity, I realized that manual computation was need to update the new % cost complete. I then dumped all activities out, and reloaded into the resource (non-labor)tab, using LUMPSUM as a resource.
My colleague then went about updating, and then, no matter how I’d set up the Activity type (always Resource dependent) and the duration type and the % complete type, I couldn’t get the resources to update.
The tech support person said that I couldn’t use money as a resource and update % to derive amounts (i.e. 58% complete activity shows 58% actual cost to date)
I sarcastically then asked tech support if I’d have to use a spreadsheet to compute actuals. They said that was a good idea (like I was seriour), but the software won’t figure out actual costs from activity % complete. Did I misunderstand? Did I talk to the wrong person?
The "costs" in this case are an earned value that is really a cost to the owner, the amount we can bill for that much progress.
10 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?