"S" Curve in P3
In the Open Standard
Salahuddin AhmedMember for 18 years 6 months
- Created
- 0
- 1
0
Nar,
Please follow the steps to produce "S" curve in P3.
> Choose Data
> Resource Curves
> Click Display to preview the defined curves.
P3 Provides nine distribution curves. You can use them as defined, modify them, or designed and add your own distribution curves.
I hope this will work, still if you have some thing else please let me know
Salah
Please follow the steps to produce "S" curve in P3.
> Choose Data
> Resource Curves
> Click Display to preview the defined curves.
P3 Provides nine distribution curves. You can use them as defined, modify them, or designed and add your own distribution curves.
I hope this will work, still if you have some thing else please let me know
Salah
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?