Level of Effort Items
In the Open Standard
Brian YungMember for 17 years 7 months
- Created
- 3
- 1
0
Good day Gentlemen,
I used to like using Hammock items in P3. It seems that Ptimavera has taken that activity type out of P6.
As a result I am using Level of Effort activities to mimick the hammock activities.
Here are some issues that I have encountered. Maybe some of you can resolve the issue for me.
1- I have a group of activities that does not have a particular sequence; therefore I used an LOE to track the start and end of this group of activities (somewhat like using WBS). By doing so, the LOE activity shows a "faulty" total float (large amount of float).
2- When I want to make an activity a successor to this group of activities by linking them with a FS relationship, the LOE item just extends its bar to the start date of the successor (I guess this is somewhat linked to my first issue)
Is there a way to fix this?
Regards,
Brian
I used to like using Hammock items in P3. It seems that Ptimavera has taken that activity type out of P6.
As a result I am using Level of Effort activities to mimick the hammock activities.
Here are some issues that I have encountered. Maybe some of you can resolve the issue for me.
1- I have a group of activities that does not have a particular sequence; therefore I used an LOE to track the start and end of this group of activities (somewhat like using WBS). By doing so, the LOE activity shows a "faulty" total float (large amount of float).
2- When I want to make an activity a successor to this group of activities by linking them with a FS relationship, the LOE item just extends its bar to the start date of the successor (I guess this is somewhat linked to my first issue)
Is there a way to fix this?
Regards,
Brian
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?