Original Duration equal to total NOT by level

Diane ArmstrongMember for 18 years 6 months
Created
3
2
0
Using Suretrak 3.0b and we received a project from P3e. The "Original duration" column has the total duration specified at each level. We want to see only that levels duration time.

Can this be changed?

Diane

3 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Diane
    Move your mouse into the table area --> right click (or "Format") --> organize --> right side within the window column "Total" --> select top or bottom --> select "Organize now".
    This works in P3 and should work in Suretrak as well.
    Regards
    Dieterr
  2. 0
    Diane Armstrong ·
    Hi Dieter... this didn’t change my results except give me a total at the bottom of each level vs. the top.

    I may not be explaining this clearly.

    Eg. The total project has 463 hours at level 1. But Level 4 also show 463 at each of its jobs although the job doesn’t total 463... it should only show a total of 6.

    Hope this explains it better.

    Also... i know this is Suretrak but it I don’t see a category for Suretrak and P3 should be fairly simular

    Thanks for your assistance
    Diane
  3. 0
    Diane Armstrong ·
    Ok... I think we solved this one... I filtered all Hammock items and it corrected itself.

    Don’t know what Hammock activities are but thats for another lesson ;)

    Thanks Diane