monthly distributed- budgeted labor quantity

Ilter AydinMember for 19 years 11 months
Created
2
3
0

How can i get the monthly distributed data ( resource usage spreadsheet) to excel in Primavera 5?
I assigned different resource curves to my resources. I can easliy see the monthly budgeted labor units by using resource usage spreadsheet in the activities module but i cannot get this data to excel.

Thanks in advance

2 replies

Oldest first
  1. 0
    Niek Zonneveld ·
    Last time I’ve tried, a plain copy/paste did the job.

    Otherwise (i.e. when your selection is very big) you’ll need to create a time-distributed report and print it out as text with CSV. (and then open this file with Excel)

    H.T.H.

    Niek.
  2. 0
    Ilter Aydin ·
    I created time distributed report. It’s ok.
    I appreciate for your help Niek.