Primavera 5

Mohamed NizamMember for 19 years 7 months
Created
1
2
0
In Primavera 5, Enterprise > Resource > Details > Material > Unit Measure >Cubic yards, Feet
Doubt 1)But I want Cubic Meters, Meter in that dropdown list

Doubt 2 ) Enterprise > Resource > Details > currency only specific currencies only mentioned. But I need to add more currency to my choice

Can some one suggest solution

1 reply

Oldest first
  1. 0
    Dieter Wambach ·
    Mohamed
    Admin --> Currencies and
    Admin --> Admin Categories --> Units of measure

Log in or join to reply