RESOURCE REPLACEMENT IN P5
In the Open Standard
Suresh Sankarankutty PMPMember for 20 years 2 months
- Created
- 5
- 6
0
Hi all,
I am with an interesting question today.
I want to give an generic resource for all activities during the scheduling time and how can replace the resource in later stage after strating the project.
I am using P5 Enterprise.
Eg;
Activity 01 - resource assigened is - labor and project started on 01/01/08 the Data date is 5th jan. Now i want to replace with labor with Fitter without affecting any % complete or actual units on the project. Is there any idea ??
Regards
Suresh
I am with an interesting question today.
I want to give an generic resource for all activities during the scheduling time and how can replace the resource in later stage after strating the project.
I am using P5 Enterprise.
Eg;
Activity 01 - resource assigened is - labor and project started on 01/01/08 the Data date is 5th jan. Now i want to replace with labor with Fitter without affecting any % complete or actual units on the project. Is there any idea ??
Regards
Suresh
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?