RESOURCE REPLACEMENT IN P5

Suresh Sankarankutty PMPMember for 20 years 2 months
Created
5
6
0
Hi all,
I am with an interesting question today.
I want to give an generic resource for all activities during the scheduling time and how can replace the resource in later stage after strating the project.
I am using P5 Enterprise.


Eg;
Activity 01 - resource assigened is - labor and project started on 01/01/08 the Data date is 5th jan. Now i want to replace with labor with Fitter without affecting any % complete or actual units on the project. Is there any idea ??

Regards
Suresh

5 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Hi Suresh
    I don’t really understand your question: Labour worked e.g. 6 hours and now you say the fitter was it? Then you’ll remove the actual units --> replace by fitter --> assign the actual units again --> Schedule. In reports you’ll find the actuals under the data date.
    Within the window "Assign resources" you’ll find the icon on the right side.
    Was this your question?
    Regards
    Dieter
  2. 0
    Suresh Sankarankutty PMP ·
    Hi Diater,
    Sorry if the qst made you confused.
    All i want to know is how can replace one resource with another in the middle of a project.

    Eg:
    Software Engineer (Jose) is assigned for acivity 01 . When duration of the task became 50% he left job. Now i want use another guy (Eg: Alex) in replacement of jose. How can i make it possible without affecting the performance % complete or some other crap result.

    Hope you got my qstn.
    Cheers
    Suresh
  3. 0
    David Forrest ·
    Assign second resource and allocate remaining days, remove remaining days from original resource.
  4. 0
    Dieter Wambach ·
    Hi Suresh
    It depends on the actuals:
    - no actual units: just replace A by B (icon just above the help sign within the assign resources window)
    - With actual units: The most accurate would be: Put an end-date to the assignment and make a new one with the new resource. To replace A by B, you’ll have to remove the actual units first - and later assign them to the new resource.
    Hope this will help
    Regards and a nice "day of work"
    Dieter
  5. 0
    Dieter Wambach ·
    Sorry David
    I couldn’t see your answer when I wrote mine
    Regards
    Dieter