Exporting Activities in P6
In the Open Standard
Sara DeanMember for 21 years 11 months
- Created
- 7
- 1
0
Hi
I am currently setting up a portfolio of projects in P6. I have 21 schedules in my EPS which are 20 project schedules and one summary schedule.
Each project schedule is managed by a scheduler located remotely around the state who in turn manage the EPCM planners. They will submit their schedules routinely. The project schedules must conform to our global codings, resource codings etc. They can apply their own codings at a project level. In the global coding a Level 2 code is applied to filter out level 2 activities in the project schedules which are then imported in to our summary network schedule. It is anticipated each project schedule will have 5000+ activities and the summary network schedule at the most 5000 activities. The summary network schedule is a summary of all 20 projects around the state. From this summary network schedule, misc filters and layouts will be produced for PM’s and GM.
I’ve applied a filter for the level two activities out of a project schedule which works. I want to know if I can export only those activities through the export function straight in to my summary network schedule without the use of excel. I don’t want the project codes exported in those activities, only the global codes. Has anyone ever got in to the scripts of P6/P5 and re-written one?
Sara
I am currently setting up a portfolio of projects in P6. I have 21 schedules in my EPS which are 20 project schedules and one summary schedule.
Each project schedule is managed by a scheduler located remotely around the state who in turn manage the EPCM planners. They will submit their schedules routinely. The project schedules must conform to our global codings, resource codings etc. They can apply their own codings at a project level. In the global coding a Level 2 code is applied to filter out level 2 activities in the project schedules which are then imported in to our summary network schedule. It is anticipated each project schedule will have 5000+ activities and the summary network schedule at the most 5000 activities. The summary network schedule is a summary of all 20 projects around the state. From this summary network schedule, misc filters and layouts will be produced for PM’s and GM.
I’ve applied a filter for the level two activities out of a project schedule which works. I want to know if I can export only those activities through the export function straight in to my summary network schedule without the use of excel. I don’t want the project codes exported in those activities, only the global codes. Has anyone ever got in to the scripts of P6/P5 and re-written one?
Sara
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?