Budgeted units = actual units
In the Open Standard
Naveen SubbaiahMember for 21 years 9 months
- Created
- 7
- 2
0
Hi,
I have set up percent complete type as units & most of activities are completed (100%). But the progress at the summary level is still very low because while updating the resource units have not been updated. So is there any way (global change) to apply budgeted units to actual units to 100% completed activities (not apply actuals).
Regards
Naveen
I have set up percent complete type as units & most of activities are completed (100%). But the progress at the summary level is still very low because while updating the resource units have not been updated. So is there any way (global change) to apply budgeted units to actual units to 100% completed activities (not apply actuals).
Regards
Naveen
7 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?