Retainage / Retention costs in P6

Ashish AbrahamMember for 19 years 10 months
Created
4
2
0
Hello everyone,

How would I include retainage (retention cost) for each activity of a project, in P6? Would I use Cost Accounts or Expenses?

Please advise.

Thanks!

4 replies

Oldest first
  1. 0
    K D ·
    Hi.
    I did not check in P6 yet but I’m sure you can do it if you have Primavera Contract Manager, an seperate module which can be linked to P6.
  2. 0
    David Kelly ·
    There is no problem in P6 in having an activity "Finished" i.e. having a finish date, AND still having a remaining cost.

    So I would use resources.

    In addition, resources can be placed beyond the finish date of the activity, so it is possible to have, say, 10% of the resource cost happening 60 days after the end of the activity.

    Have Fun!!!
  3. 0
    Ashish Abraham ·
    Thanks for the replies! I really appreciate your help.
  4. 0
    K D ·
    Yeah this’s a good idea