Total Float
In the Open Standard
Mohammed Abo El MagdMember for 21 years 10 months
- Created
- 6
- 1
0
Dear all,
I’d like to discuss this issue with you. As soon as you update the activities with actual start and finish, the total float indicates nil. Should not the total float indicate negative or positive values as delay occurred or preceding the schedule?
Regards
Mohamed
I’d like to discuss this issue with you. As soon as you update the activities with actual start and finish, the total float indicates nil. Should not the total float indicate negative or positive values as delay occurred or preceding the schedule?
Regards
Mohamed
6 replies
Oldest firstLog in or join to reply