Hi Planners

What is the maximum total float value(in days )an activity can have in a project of 1year duration

Regards

C.Mallesha

5 replies

Oldest first
  1. 0
    Satya Narayana ·
    Can u eloborate further. Theoretically U can have any float but that depends on many things, what project whats your construction sequence, ur resources and the list goes.............

  2. 0
    Steven Oliver ·
    Well, if you do something today, that you dont need for a year, what do you think your float would be ?
  3. 0
    Satya Narayana ·
    364 days thats waht i eman when i said it can be any thing.
  4. 0
    Mallesha Chandra Shekar ·
    i mean is there any rule that max total float to be limited to some (%) percentage of project duration

    Regards

    C.Mallesha
  5. 0
    Satya Narayana ·
    No such rule