Actual Duration in P6
In the Open Standard
Suresh Sankarankutty PMPMember for 20 years 2 months
- Created
- 3
- 2
0
Hi
I imported one project from MSP to p6 the actual duration shows in p6 is different from MSP. Can any one tell me how p6 calculate the actual duration ? In MSP the actual duration = Original Duration * % Complete . And in MSP the remaining duration = Original Duration - Actual duration . Could any one explain how its in P6 ?
Suresh
I imported one project from MSP to p6 the actual duration shows in p6 is different from MSP. Can any one tell me how p6 calculate the actual duration ? In MSP the actual duration = Original Duration * % Complete . And in MSP the remaining duration = Original Duration - Actual duration . Could any one explain how its in P6 ?
Suresh
3 replies
Oldest firstLog in or join to reply