Milestone Activities with invalid relationships?

Ladi SodipoMember for 18 years 11 months
Created
4
2
0
I get this error in my schedule log and i cant determine what relationships are invalid in my plan, wondering if this is a common error in p5 and how best to fix this, any suggestions.

4 replies

Oldest first
  1. 0
    Dieter Wambach ·
    Ladi
    Don’t worry! For milestones not all relationships are available. If an activity had a different type before you may have assigned an not allowad relation. For scheduling start or finish of a milestone is the same. Until now I never found a susequent error to this one. Just ignore it.
    Regards
    Dieter
  2. 0
    Satya Narayana ·
    If you have FS relationships with in the mile stones this is displayed as invalid relation ship in schedule log/report.

    This is one of the cases.
  3. 0
    Anoon Iimos ·
    it depends if it is a start milestone or a finish milestone, you have to assign corresponding relationship for start and or finish, ask yourself if it is valid to assign a FF for a start milestone?
  4. 0
    Garry Macdonald ·
    It happens when you have a finish milestone with a FS relationship to another finish milestone. This should be a FF relationship. Its a similar fix with start milestones etc.