Resource assignment inquiry
In the Open Standard
Yusuke KamuiMember for 18 years 5 months
- Created
- 4
- 1
0
Hi,
I have this task (Fixed Unit) and there are 2 resources assigned it to. Total budgetted units = 1000 hours. Scheduled to start on June 1. Date now is May 27.
Resource A, budgeted units = 500 hours, will work for the whole duration of the task
Resource B, budgeted units = 500 hours, but will work only on a specific time frame of the task.
How to do it?? Say for example Resource B needs to work on the task from June 12 to June 19 ONLY, then after that he will be removed on this task and all uncompleted / balance units will be transferred to Resource A.
I have this task (Fixed Unit) and there are 2 resources assigned it to. Total budgetted units = 1000 hours. Scheduled to start on June 1. Date now is May 27.
Resource A, budgeted units = 500 hours, will work for the whole duration of the task
Resource B, budgeted units = 500 hours, but will work only on a specific time frame of the task.
How to do it?? Say for example Resource B needs to work on the task from June 12 to June 19 ONLY, then after that he will be removed on this task and all uncompleted / balance units will be transferred to Resource A.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?