Negative Float on Milestone?
In the Open Standard
Victoria TanMember for 18 years 7 months
- Created
- 12
- 4
0
Hi Guys,
I have a milestone in my P5 schedule which finish date is correct as planned. However, the milestones and all of its predecessors (20#) are showing negative float, while all of its successors are showing positive float.
There are no constraints in the logic path, no must finish by date on the project, and I am scheduling using progress override.
Any ideas please?
Vicky
I have a milestone in my P5 schedule which finish date is correct as planned. However, the milestones and all of its predecessors (20#) are showing negative float, while all of its successors are showing positive float.
There are no constraints in the logic path, no must finish by date on the project, and I am scheduling using progress override.
Any ideas please?
Vicky
12 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?