Managing PMO Team security profiles, privileges

Jose RamirezMember for 18 years 1 month
Created
5
2
0
Ello,

I guess I have been given the role as a Primavera Administrator and I need to put together the following for the Project Management Office (PMO):

The Creation of standards for WBS, Resource Codes, OBS, EPS, Users, Security Profiles, Activity Codes, and anything else. (These are not the problem)

Also I need to managing security profiles, privileges, resource/role pools, timesheet apps, creating standard layout and standard reports.

My question is that I do n’t know what each member of the PMO team needs for security profile and privileges or what information they will need to view: (I always been able to do everything on Primavera. So, I have always given meself all the allowable privileges)…

After you create the Security Profile for each user what Privilege they should be allowed? Also when you create the Users what Global Access could they be assigned? For each of the PMO Team what specify the resource that the User (PMO member) will be able to access? Finally licensing should it be Concurrent User for Team Member or Project Management (40 Licenses available).

This is what I think the team looks like please feel free to add other roles from the PMO team I have missed:

- Lead Program Planner/Scheduler - maintain/analyze the project schedules and resources
- Project Planner/Scheduler/s – development of project schedules/maintain schedules/analyze project schedules including roles/resources at a project level.
- Primavera Administrator [ Me, x} ] - to provide support for P6 issues (i.e. call tech support)/DB/Report or Layout standard templates/historical data library
-Project Manager
-Cost Control Office
-Procurement Office
-Engineering Office

Thanks to all that are able to help,

JoseR o_O

5 replies

Oldest first
  1. 0
    Dieter Wambach ·
    José

    The roles seem ok, maybe to add a resource planner (Head of Team or Department). Cost Control may work with a read-only profile.

    You can start with those profiles:

    - Read everything maybe without costs: The whole team
    - Two "Admin Superusers" - one might be sick, on business trip,...
    - Each planner and scheduler should have her/his test area with a right "Project Superuser" - or create a second database for testing.
    - Be careful with the right to delete (projects, activities, codes, resources). Only Admins should be allowed
    - Study the concept of "secure codes"
    - Study the Help function, it is very good.

    Don’t forget to create and to enable a batch job (Tools --> Job Service) which summarizes every night.

    I’m very surprised to see you start with P3e.

    Good luck!

    Dieter


  2. 0
    Jose Ramirez ·
    Okay PPL of Planning Planet and Dieter(Thank you for your guidance), This is what My Security Profiles and Privileges are staring to look like:

    I place a (?) on privileges I wasn’t sure about. So, if anyone would like to advise me on: Sec. Profile, if they should have/not have the PRIVILEGE I have ALLOWED THEM, listed below for each of the Profiles. Please, Let me know.

    Security Profile:

    Cost Control Account Manager (CCAM)

    Privilege:
    Store Period Performance
    Edit Period Performance
    View Project Costs/Financials
    Edit Project WBS Financials
    Edit EPS Financials
    Edit Project Expenses

    Project Controls Coordinator (PCC)

    Privilege:
    The PCC has all rights n privilege (edit access to all data, including administration rights)


    Project Manager (PM)

    Privilege:
    Summarized Project
    Edit Project Details Except Financials
    Schedule Project
    Apply Actuals?
    Maintain Project Baseline?
    Assign Project Baseline?
    Edit Project Work Products and Documents
    View Project Costs/Financials
    Check In/Check Out Project
    Assign Issue Forms
    View Timesheets In Report
    Project Top-Down Estimation?
    Edit Project Thresholds, Issues and Risk?
    Add/Edit Project Level Layout

    Lead Project Planner/Scheduler

    Privilege:
    Create Projects Within EPS
    Summarize Project
    Edit Project Details Except Finacials
    Adminster Project Externals Applications
    Schedule Project
    Level Resources
    Apply Actuals
    Store Period Performace?
    Maintain Project Baselines
    Run Baseline Updates
    Assign Project Baseline
    Edit Project Work Products and Documents?
    Add/Edit Project Template Documents
    Edit Project Activity Code
    View Project Cost/Financials
    Edit Project Activity Codes
    Add Project Activity Codes
    Edit Project WBS Except Financials
    Edit Project Expenses
    Edit Project Activity Relationship
    Add/Edit Project Activities Except Relationship
    Add/Edit Project Level Layout
    Monitor Project Thresholds?
    Edit Project Reports
    Check In/Check Out Project
    Assign Issue Forms
    View Timesheets In Report
    Import/View Contract Manager Data
    Project Top-Down Estimation
    Edit Project Thresholds, Issues and Risk
    Create Work Group?
    Modify Project Workspace and Workgroup Preferences?

    Project Planner/Scheduler

    Privilege:
    Schedule Project
    Apply Actuals
    Maintain Project Baselines
    Run Baseline Updates
    Assign Project Baseline
    Edit Project Work Products and Documents?
    Add/Edit Project Template Documents
    View Project Cost/Financials
    Check In/Check Out Project
    Edit Project Activity Relationship
    Add/Edit Project Activities Except Relationship
    Delete Project Activities
    Add/Edit Project Level Layout

    Resource Manager

    Privilege:
    Delete Resource
    Add Resource
    Edit Resource
    Approve Resource Timesheet
    Edit Global Reports
    Edit Global Tracking Layouts
    Edit Roles
    Edit Global Calendar
    Edit Resource Calendar
    Edit Timesheet Dates
    Edit Project Codes
    View Resource and Role Costs
    Schedule Project
    Level Resources
    Perform Acitivity Resource Request
    Edit Resource Assignment For Resource Planning
    Edit Committed Flag for Resource Planning?

    Thank you all,

    JoseR

    (\__/)
    (+’.’+)
    (")_(")




















  3. 0
    Dieter Wambach ·
    José

    What you’ll allow to your users depends on the organization you are working for. Basic principle for me allways was: Read access: liberal, Write: restrictive, Delete: Very restrictive. The roles that you defined seem quite reasonable. Just some remarks/questions:

    CCAM: Needs
    - View resource and Role Costs
    - Edit Project Activities

    PCC:
    NOT: Edit Users, Edit Profiles
    Shall she/he vreate projects and condes?

    PM:
    Plus: Edit WBS, Apply Actuals, Maintain and Assign BL, Monitor Risks...

    Edit codes, resources, Imp/Exp, create projects should be restricted to yourself and your "Deputy"

    RM:
    Edit Committed Flag If you’ll use the web interface, then he’ll need it otherwise it’s not accessible.

    Regards

    Dieter
  4. 0
    Jose Ramirez ·
    Hi Dieter,

    Thank you so much again. This is very helpful in creating the best possible security profiles and privileges for this folks. I also read the adm guide it was also helpful in getting this far.

    I wanted to ask you about the EPS Secure Codes:

    "A global or EPS-level activity code that is accessible only to certain users. If an EPS-level or global activity code is marked as a secure code in the Activity Code Definitions dialog box, the user will need the appropriate access rights to view, edit, delete and assign this code and its values."

    Would you be able to provide me with a few examples of what these secure codes are, since I don’t know what information one would want to hide with these codes?

    Thank you Dieter,

    Hope you had a great weekend.
  5. 0
    Dieter Wambach ·
    José

    Thanks, José; it was filled with work.

    These codes are valuable in case of cooperation - if customer or a subcontractor receive a project-file or have access to the database. In my opinion the most important characteristic of these codes is: They are not exported.

    Examples might be:
    - Characteristics of persons (workers) - regulations to keep personal data secret.
    - Informations (classifications) on business partners which must be kept as company’s secret.
    - Financial classifications.

    Much success with your project!

    Regards

    Dieter