Import excel data to Activity code value

Ranish KTMember for 23 years 9 months
Created
6
21
0
How to transfer/import excel data (Code and description) to activity code Value in P6.

I have about 5000+ itesm to be added as value for one of the activity codes.

Regards

Ranish

6 replies

Oldest first
  1. 0
    David Forrest ·
    Try the SDKU60 , refer to prim10191.
  2. 0
    Marshall Zewe ·
    I think that the only way to do what you are asking is to add the codes to the P3 dictionary, create a dummy job using one of those codes, and then import the P3 job into P6. All of the codes will be there (might need to be re-arranged). I have done this once before (I think...). Someone else please correct me if this is not right.
  3. 0
    Alex Wong ·
    Marshall

    That’s is one of many ways to importing code to the system.

    Using SDK, API, Import/Export, Third Party integration tools are just few other ways to do what is original ask for.

    Each solution of course is different, in terms of time / effort / cost.

    HTH

    Alex
  4. 0
    David Kelly ·
    you need Dictionary?.XLS from the Primavera Knowledge base. Loads any codes except wbs. you need P3 for that
  5. 0
    Alhasan Abdalla ·

    here is the link for the

    here is the link for the latest sdks

    activity6x.xls , dictionary6v7.xls , wbs.xls , project.xls

    http://www.eh.com.au/software.html

    Regards

  6. 0
    Alhasan Abdalla ·

    here is the link for the

    here is the link for the latest sdks

    activity6x.xls , dictionary6v7.xls , wbs.xls , project.xls

    http://www.eh.com.au/software.html

    Regards