Organize using Activity ID in P6

Ranish KTMember for 23 years 8 months
Created
3
3
0
In P3, if the activity id is ingeniously developed, we can oraganize the project activiites WITHOUT the help of activity codes or WBS.

Is this feature possible in P6 ?

3 replies

Oldest first
  1. 0
    Ronald Winter ·
    No, you cannot do this with P6. P6 does not support Activity ID codes.
  2. 0
    Alex Wong ·
    Dear All

    The reason we drop P3 is because it is limited with codes so that we have to use intelligent activity id.

    We are no longer require to do such thing in the new system

    Good Luck, for planner still try to build activity code within the activity ID

    Alex
  3. 0
    Ronald Winter ·
    I concur with your statement. Why would anyone want to use intelligent activity codes that serve a dual purpose and do not take up any additional space on your display screen? Who needs elegance when we can have the brute force of SQL databases churning away on our queries?