Resource level on progressed schedule
In the Open Standard
Naveen SubbaiahMember for 21 years 9 months
- Created
- 3
- 4
0
Hi,
I have a progressed schedule with units as % complete type. Due to some delays in the project & resource constraints I have carried out resource levelling using activity levelling priority(this is done on a copy of the project) and that has fulfilled the project objective.
Now is there a way to transfer these levelled dates from the copy to the original project ?
Thanx in advance.
Regards
Naveen
I have a progressed schedule with units as % complete type. Due to some delays in the project & resource constraints I have carried out resource levelling using activity levelling priority(this is done on a copy of the project) and that has fulfilled the project objective.
Now is there a way to transfer these levelled dates from the copy to the original project ?
Thanx in advance.
Regards
Naveen
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?