Resource level on progressed schedule

Naveen SubbaiahMember for 21 years 9 months
Created
3
4
0
Hi,

I have a progressed schedule with units as % complete type. Due to some delays in the project & resource constraints I have carried out resource levelling using activity levelling priority(this is done on a copy of the project) and that has fulfilled the project objective.
Now is there a way to transfer these levelled dates from the copy to the original project ?

Thanx in advance.
Regards
Naveen

3 replies

Oldest first
  1. 0
    Satya Narayana ·
    2 exports and 1 import to/from excel should solve your problem
  2. 0
    Naveen Subbaiah ·
    I am working on 4.1 which does not have the export to excel feature.
  3. 0
    Satya Narayana ·
    Sorry, I have necer worked on 4.1 but i feel it should supports some export format, may be a csv