Couple of questions for P5
In the Open Standard
Yusuke KamuiMember for 18 years 5 months
- Created
- 3
- 4
0
Hi,
I hope someone can clarify on this as well give some inputs:
1. What is the difference between "Schedule" - function key F9 and "Update Progress" under the Tools option ?
2. I have 70+ tasks or activities and the activity status of all of them are "In Progress". How to easily change their status as "Not Started"? I found out I need to change each one of them manually! A very tiring thing to do. Can it be changed like a copy-paste thing similar to MSProj?
3. Similar to #2 above, how to change the Start Date of all of those 70+ activities to "June 15, 2008" easily? I found out in P5, copy and paste does not work! A very basic function for a win apps.
Thanks in advance.
I hope someone can clarify on this as well give some inputs:
1. What is the difference between "Schedule" - function key F9 and "Update Progress" under the Tools option ?
2. I have 70+ tasks or activities and the activity status of all of them are "In Progress". How to easily change their status as "Not Started"? I found out I need to change each one of them manually! A very tiring thing to do. Can it be changed like a copy-paste thing similar to MSProj?
3. Similar to #2 above, how to change the Start Date of all of those 70+ activities to "June 15, 2008" easily? I found out in P5, copy and paste does not work! A very basic function for a win apps.
Thanks in advance.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?