Skip to content

Brand New to P5 - Import questions

Maya CMember for 19 years 4 months
Created
6
1
0
I am brand new to P5 and I am stumbling while importing from Excel files. I have these questions.

1) Should WBS codes be manually created (and referenced in the Excel Files)in P5 before exporting activities?

2) For some reason, my START dates are not importing correctly. They are defaulting to the DATA date. I have a DURATION column and FINISH colum and they are populating correctly, however all my START dates are defaulting to data dates.

I would really appreciate if anybody can shed some light on these issues.

Many thanks.

6 replies

Oldest first
  1. 0
    David Moses ·
    Hi There,

    Did you check the relationship of activities?

    I mean, while importing or exporting are you also importing or exporting predecessors or successors of activities.

    It may cause such problem.

    Regards,
  2. 0
    Maya C ·
    I am not importing relationships, just activities.

    Can you create WBS by importing?

  3. 0
    David Moses ·
    Hi There,

    You are importing activities.Ok.

    But if there is no relationship b/w activities, whether you import it or not, it is logical to see the start dates as data dates on the program.

    Start dates, durations and finish dates are not enough to create a cpm. Relationship of those activites has to be defined as well.

    Hope this helps
  4. 0
    Oliver Melling ·
    I agree with David,

    you must have relationships between your activities in order to schedule the work. Otherwise all activities will move to the data date as there is nothing telling them they can’t start immediately.
  5. 0
    Maya C ·
    That really helps. This forum is great!

    Thanks for your time, David and Oliver!
  6. 0
    David Moses ·
    That is great !!!

    Keep on planning.....

    Regards

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?