Skip to content

Productivity factor in P5

Yusuke KamuiMember for 18 years 5 months
Created
3
4
0
Hi,
Does anyone know how to factor the productivity efficiency in Primavera (P5)?
Currently I have an overall budgeted units for project amounting to 100,000 hrs. Considering an efficiency of only 85% so I need to add 15% on top of the budgeted units to equal to 100,000 + 15% = 115,000 hrs. So how to distribute or change each and every task in my schedule to equate the budgeted units total to 115,000 hrs?? Do I need to add 15% in every task’s budgeted hours?? Take note there are some task having actuals already. All of the task is a resource dependent, fixed unit type.

Thanks!

3 replies

Oldest first
  1. 0
    David Forrest ·
    You can try increasing resource max units/time to 115% and recalculate.
  2. 0
    Larry Rino ·
    Sorry but you need to input the new figures (+15%) manually...

    Good day
  3. 0
    Shiv Rao ·
    You need to use Global Chaneg .

    And select Activity Resource Assignment .

    Change Budgeted units for All REsources from 1 to 1.15

    regards

    shiv

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?