Productivity rates of manpower

Muhammad SaqibMember for 7 years 11 months
Created
12
3
0

Hello Everybody,

I am new here in this platform and i need to ask some questions and i would appreciate if you answer my questions.

 

I have choosen my career as a planning engineer in building side. I have done BSc Civil Engineering and then Masters in Project management. I have only 2 months of experience.

 

I need the productvity rates of manpower in building construction because i have been asked many times in an interview how many manpower you would use in anonymous activity and i had no answer.

 

 

Thanks

12 replies

Oldest first
  1. 0
    Anoon Iimos ·

    Activities in building

    Activities in building construction are certain. Volume of works can be calculated exactly. So manpower always depend on the volume of works and maneuverability. However, technology becomes sophisticated that sometimes reduces the number of manpower as compared from traditional or conventional ways.
  2. 0
    Zoltan Palffy ·

    look on this site under the

    look on this site under the tab up top labeld Build Times

  3. 0
    Muhammad Saqib ·

    Thanks but i didn't find

    Thanks but i didn't find anything . 

  4. 0
    Muhammad Saqib ·

    Yes you are right but i have

    Yes you are right but i have to start form somewhere. 

    Atleast there are some standards which we used at the start of the project. I really don't have the site experience

  5. 0
    Rafael Davila ·

    Consider using RS Means as a

    Consider using RS Means as a reference in the absence of company records.  It is critical you understand that the components work as as a group.  Increasing or decreasing individual team members within the crew most probably will invalidate average crewhours per unit of work, these numbers are valid for the specific crew composition, nothing more, nothing less.

    Click to Download - RS Means PowerPoint Presentation

    Good Luck.

  6. 0
    Muhammad Saqib ·

    Dear Rafael, Thanks for your

    Dear Rafael,

     

    Thanks for your reply

    but link is not opening. I think there is some kind of an error .

  7. 0
    Mohammed Ali ·

    What is your Email and I will

    What is your Email and I will send you some files?

  8. 0
    Rafael Davila ·

    The link is no longer

    The link is no longer available.

    Instead please take a look at the folllowing link. There you will see a sample page showing crew composition and daily output.

    Be reminded that crew production rate is a function of the crew composition.  Changing a single component usually will result in a change in production rate. Usually the change is not linear to a change in manpower even if only manpower resources are used, more so if production equipment are a component of your crew.

    RS Means - How to use the Unit Price pages

  9. 0
    Muhammad Saqib ·

    Dear Mohammad Ali,Thanks for

    Dear Mohammad Ali,

    Thanks for the response. I really appreciate if you send me some files.

    Here is my email address

    (Saqib.bhatti92@gmail.com )

  10. 0
    Muhammad Saqib ·

    RafaelThanks and got it.

    Rafael

    Thanks and got it.

  11. 0
    Mohammed Ali ·

    sent

    sent

  12. 0
    Muhammad Saqib ·

    Received Ali Brother.Thanks

    Received Ali Brother.

    Thanks Alot 

    God Bless U