Graphs & S Curves

Shiv RaoMember for 18 years 7 months
Created
1
2
0
Hi to All,

What are the best S curves drawn from Primavera.

Please send some samples at jayshiv26@hotmail.com.

Also if we want to change Globally the man hrs for one particular resource with a factor of 0.9.
How can that be done?

Regards

Shiv Rao

1 reply

Oldest first
  1. 0
    David Podmore ·
    Shiv,

    To do a global change....

    (1) In "Select Subject Area" choose "Activity Resource Assignments"
    (2)Where - Resource ID Name = (your target resource)
    Then - Budget Labour Units = Budget Labour Units x 0.9

    Check the result is what you expected and commit.

    David

Log in or join to reply