Skip to content

Leveling priorities

Mohsen NourbakhshMember for 19 years 7 months
Created
5
3
0
Hi all,
I am having bit of an issue to set leveling priorities at Activy Codes levels. i.e. having a number of different equipment to be overhauled during a turnaround i like to level the plan so that it reflect the desired priorities.
I like to avoid creating a new activity code like "Priorities" to avoid extra work as I suspect primavera (P6) must have allowed for this .. maybe shift up/down???
any ideas highly appreciated

5 replies

Oldest first
  1. 0
    David Kelly ·
    Mohsen,

    If you use an existing activity code for resource levelling priorities, it will use the collating sequence you have left the activity code dictionary in.
  2. 0
    Shiv Rao ·
    Mohsen,

    I am also working on similar turnaround for an LNG Plant .
    Allmost my entire resource are staggered in the ist 10 days of the total 40 days as all workscope are expected to start on zero date and are 7/10 day activity.

    I wanted to go for Resource levelling but the priority are to be fixed if we need to use the equipment as priority or some thing else .
    I am not sure how r you going to handel .

    regards

    Shiv
  3. 0
    Mohsen Nourbakhsh ·
    David,
    Thanks for the input. I hope that is how priorities are set which could help us alot
    Shiv,
    What I have in mind would be to also look at a combination of resource leveling, float paths, critical path to determine how to spread the work and to justify the outcomes. It will get more complex if looking at more than one project/turnaround at a time since the resources come from only 1 resource pool and thsi is yet to be worked on and see the results
  4. 0
    Andrew Podolny ·
    There is ’built-in’ Activity Leveling Priority field which should be used. You can find the column under General section.
    Regards,
    Andrew
  5. 0
    Syam Mohan ·

    Hi all,       How can i

    Hi all,

           How can i reduce the manpower for a specified month for an ELV project. I tried to reduce many parallel activities,but i didn't traced any massive change. please help me with your valuable suggestions.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?