Assigning Resouces in more than 1 activity

Amanullah MughalMember for 21 years 10 months
Created
5
2
0
Dear Planners,

I have to add verious resouces to around 1000 activities. It was possible in P3 to assign resouces applying the feature of Global Change within seconds. But assigning resouces to activities one by one is too labourious. Is there any option in P6 to add resouces applying Global change?

If anybody has the idea, please list down the steps for the same using P6.

Aman

5 replies

Oldest first
  1. 0
    Alan Binnie ·
    Obviously a difficult one as no-one has replied.

    I can get global change to add a resource to all activities - but in doing this it doesn’t want to just add the new one - it want’s to replace the existing ones!!

    What good is that? Does anyone know how to do it?
  2. 0
    Arnold Puy ·
    Hi Aman,

    Resource allocation using global change, this feature is not supported in P6.

    You can use Assign Resources. Try the following steps:

    1. Select & Filter all the activities you wanted to assign the Resources.
    2. Select the "Assign Resources" icon located at the right corner of your screen.
    3. Select the resources to be assigned & tick assign.

    Hope this help.


    Arnold
  3. 0
    Alex Wong ·
    Aman & Alan

    No one answer your question may not because of too difficult but instead the other way around.

    What Arnold provide is ideal way if you try to assign the same resource accross a filter list of activities.

    Put it this way, assign multiple resource against multiple activity is a lot easier in P5 compare to P3

    HTH

    Alex
  4. 0
    Amanullah Mughal ·
    Hi Arnold,

    Thanx a lot, it works.

    Aman
  5. 0
    Arnold Puy ·
    You are welcome