Can Primavera Contractor save XER files

Ivan BothaMember for 21 years 1 month
Created
1
4
0
I am am considering to buy the Primavera Contractor - The "P6 lite" version and would like to know if it can export and import XER files from and to P6.

The consultants I am working with require an XER file for P6

I know the contractor deluxe can only have 2000 activities. For my work that is OK.

Kindly advise.

1 reply

Oldest first
  1. 0
    Paul Harris ·
    Primavera Contractor is designed for people like you who do not need the Enterprise functions and it will export an XER file. It is a shame that Primavera has hobbled it to 2000 activities which makes it useless for any significant programme. Asta PowerProject will also open, edit and save to an XER file and in my opinion is a product that is more suited to construction contractors than the new Primavera software.

    Paul E Harris
    Eastwood Harris Pty Ltd, Melbourne, Australia
    Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
    www.eh.com.au

Log in or join to reply