Total budgeted units in a specific time frame
In the Open Standard
Yusuke KamuiMember for 18 years 5 months
- Created
- 4
- 5
0
Hi,
I’m using P5 and I want to readily see the total budgeted labor units of the whole project in a specific time frame or period. Say for example from Aug 1 to Aug 12. How to do it?
I heard that you need to calculate it manually. But this is ok for 1 activiy, but if we are talking about the whole project consisting of 800+ activities this is not practical anymore. So any idea?
Thanks.
I’m using P5 and I want to readily see the total budgeted labor units of the whole project in a specific time frame or period. Say for example from Aug 1 to Aug 12. How to do it?
I heard that you need to calculate it manually. But this is ok for 1 activiy, but if we are talking about the whole project consisting of 800+ activities this is not practical anymore. So any idea?
Thanks.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?