Scheduling without actual units
In the Open Standard
Beck LeeMember for 18 years 4 months
- Created
- 2
- 3
0
Hi,
I am wanting to progress schedules without recording actuals (as the PMO maturity isn’t there yet and the interface with the timesheeting system is yet to come).. I have set all resources to NOT auto-compute actuals, yet when I progress activities, actual units still appear..
I have task dependant activities with fixed duration and units/time (as I want remaining units to = remaining duration * original units/time).. Do I have to run a global change to clear out actual units?.. have I set up the activities correctly to acheive this simple progressing method?
I am using P6.1
Thanks,
I am wanting to progress schedules without recording actuals (as the PMO maturity isn’t there yet and the interface with the timesheeting system is yet to come).. I have set all resources to NOT auto-compute actuals, yet when I progress activities, actual units still appear..
I have task dependant activities with fixed duration and units/time (as I want remaining units to = remaining duration * original units/time).. Do I have to run a global change to clear out actual units?.. have I set up the activities correctly to acheive this simple progressing method?
I am using P6.1
Thanks,
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?