The sooner the better

Hannes de BruyneMember for 21 years 2 months
Created
3
1
0
Hello, does anybody have a proposal how to make only one milestone or constraint
"the sooner the better"?

Regards

3 replies

Oldest first
  1. 0
    Alphons Bruns ·
    Be more specific please

    regards Alphons
  2. 0
    Hannes de Bruyne ·
    I have an activity with a lot of float - for technical reasons - but it is good to start this activity as soon as possible, to be earlier than compatitors
  3. 0
    Alphons Bruns ·
    Hello Hannes,
    Create a predessesor milestone with fs relationship to the task and put a start on constraint on it, it will turn red if the data date will pass the constraint date

    regards Alphons