Good Day to all planners

Example Activity ID is CON000010

How would I input it in the default settings of Prefix, Suffix and Increment?

My problem is the suffix you cannot put "000000" value it goes back to "0".

5 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Pacifico,

    Instead of putting it in Suffix why not put it in Prefix. Because you cannot input 000000 without accompanied by 1, 2, 3, etc.

    You can try to input CON000000 in Prefix and 1000 in Suffix and Increment of 1, 2 etc....


    Arnold
  2. 0
    Rony Roberto ·
    Hi Fhics,

    Try this, Go to Enterprise--->project * highligths your programe to set ---> go to Defaults -->Auto numbering Defaults, fill up now your Act.ID prefix,Suffix & increment.

    Hope it’s help


    Regards,

    Rony
  3. 0
    Rony Roberto ·
    Hi Fhics,

    Try this, Go to Enterprise--->project * highligths your programe to set ---> go to Defaults -->Auto numbering Defaults, fill up now your Act.ID prefix,Suffix & increment.

    Hope it’s help


    Regards,

    Rony
  4. 0
    Rony Roberto ·
    Hi Fhics,

    Try this, Go to Enterprise--->project * highligths your programe to set ---> go to Defaults -->Auto numbering Defaults, fill up now your Act.ID prefix,Suffix & increment.

    Hope it’s help


    Regards,

    Rony
  5. 0
    Pacifico Pallasigui ·
    Thank you Arnold that solves my problem



    Activity Id: CON000010

    Prefix: CON0000

    Suffix : 10

    Increment : 10


    Then when it goes down to 100 the end 0 of the prefix would be taken out.

    Thank You

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?