P6 Moving Activity

Riyadh YahiaMember for 18 years 2 months
Created
9
4
0
Hi,

At the time I make scheduling (F9) for P6 project, I notice that the activity date is moving to new date also some activities took the data date itself !!!!!! that hapen also after assigning a baseline.

Any could help ???

9 replies

Oldest first
  1. 0
    A D ·
    Go to tools--> Resources --> go to details tab and check AUTO COMPUTE ACTUALS.

    Switch OFF anto compute actuals.

    This shud solve ur problem

  2. 0
    Riyadh Yahia ·
    Hi Bhedase,

    I did as you said, but did not work.....still moving.....

    Any other solution please !
  3. 0
    Alex Wong ·
    Well

    Have you try to put a actual start date to your activity.

    that will stop the Early Start date moving as the data date move :-)

    you need to make sure you updated your schedule correctly

    Alex
  4. 0
    Riyadh Yahia ·
    Dear Wong,

    that is the point I can not Put Actual start for

    Activities didnot Start YET.

    Any Other Sugestion........
  5. 0
    Arnold Puy ·
    Hi Riad,

    Generally, the Start Date of each Activity will keep on moving as the Data Date move especially when this activity is not yet started and the predecessor of it will keep pushing when there is no progress recorded and also due to driving relationship.

    To avoid moving the Start Date, all you have to do is to adjust the LAG or change the Relationship Type. But in this case, you have to inform the Client and you should specify and justify all lags and relationship type.


    Regards,

    Arnold
  6. 0
    Ronald Winter ·
    Let me add to what Arnold just said…

    The start of any unstarted activity with no outstanding predecessor commitments is supposed to move when the data date moves. If it does not then you are talking about MS Project. Unless you have a time machine and are planning to use it to move your work crews back in time, uncompleted work cannot exist in the past. Good luck!
  7. 0
    Ian Adan ·
    Excellent Mr Winter. You just made my day.
  8. 0
    Riyadh Yahia ·
    Thanks to ENGR, winter & Engr,Puy

    for their full explanation, Now I got the Point as they

    explained in detail.

    best regards

    riad

  9. 0
    Alex Wong ·
    That why I find very hard to explain the MSP project manager to have activity not started and planned in the past....