Skip to content

Summary bar duration in P6

A DMember for 19 years 5 months
Created
0
2
0
In P6 on my computer, summary bar always displays the duration in WORKING DAYS and not calender days. In my orgz. v have 5 day calender as global calender.

Is it possible to convert summary bar duration to calender days. Is it possible to have it by having a 7 day global calender with no off??

And by the way guys, what do u prefer to have summary bar durations, WORKING DAYS or CALENDER DAYS.

???

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?