Summary bar duration in P6
In the Open Standard
A DMember for 19 years 5 months
- Created
- 0
- 2
0
In P6 on my computer, summary bar always displays the duration in WORKING DAYS and not calender days. In my orgz. v have 5 day calender as global calender.
Is it possible to convert summary bar duration to calender days. Is it possible to have it by having a 7 day global calender with no off??
And by the way guys, what do u prefer to have summary bar durations, WORKING DAYS or CALENDER DAYS.
???
Is it possible to convert summary bar duration to calender days. Is it possible to have it by having a 7 day global calender with no off??
And by the way guys, what do u prefer to have summary bar durations, WORKING DAYS or CALENDER DAYS.
???