Progress by units in P5

Muhammad FiazMember for 18 years 2 months
Created
2
2
0
I want to update progress by BOQ units for L4 construction schedule.How do i do it?
Do i define BOQ as a Labor resource and Manhours as a non Labour resource?

2 replies

Oldest first
  1. 0
    Oliver Melling ·
    The other way round.

    Labour - productive work (especially physical work done for wages)
  2. 0
    Muhammad Fiaz ·
    Thanks for your reply.
    If we define BOQ as Non-Labor and Manhour as Labor resource then while updating progress by units P5 calculates by adding both units as
    %completed = actaul (Labour+NonLbour) units/Budgeted(Labor+Nonlabour units)

    Budgeted BOQ=4000 Sqft , Mhrs=250

    Actual BOQ=2000 Sqft , Mhrs=100

    Progress( by units ) calcuted by P5 is
    (2000+100)/(2000+250)=49.41%

    But actually BOQ is 2000/4000=50%

    How can we update progress on BOQ Nonlabour resource units only and planned Labour Manohours units depending on BOQ.I want to update progress by BOQ .
    Please advise.

Log in or join to reply