Importing P3 into P6 and activity logs

Chuck LiversMember for 21 years 1 month
Created
1
1
0
I successfully imported a P3 file into P6 but I am unable to display the information I had entered as "activity log data". This used to be done through the bar label command window but I am stuck on how to display same in P6. Thank you for your assistance.

1 reply

Oldest first
  1. 0
    Donna Hernandez ·
    First add the P3 activity Log as a Notebook Topic in P6. Then go to the bars section of P6 where there are many more bars to chose from. Make sure you are selecting a bar that is checked to display. The Label will be titled Notebook - P3 Activity Log. There are more than one to select from, so be sure to pick the one that you assigned to the notebook topic.

    Good Luck,

    Donna

Log in or join to reply