assign calendars to many activities in one step

Abeer MahmoudMember for 18 years 3 months
Created
6
2
0
Dear all,

Can any body help me to assign calendars/durations....etc to many activities in one step? As we used to do in p3 by fill cell command where is this command in p5?

Thanks.

6 replies

Oldest first
  1. 0
    Hannes de Bruyne ·
    Did you try Edit->Fill Down (CTRL+E)?
  2. 0
    Arnold Puy ·
    Hi Abeer,

    You can assign calendar for the existing activities using GLOBAL CHANGE.

    Calendar = "Select Calendar"

    If you wanted to change the selected activities only then you need to filter prior to run Global change.


    Arnold
  3. 0
    Riyadh Yahia ·
    Hi Abeer,

    To add a calender in one step, try this:

    1- Add calender Column from Column (General Option.

    2-Add desired Calender to First activity on Top of the Column.

    3- Point the arrow on empty Calender Cell at the Bottom of the Calender Column.

    4- By using(SHIFT + UP ARROW) OR (SHIFT + MOUSE POINTER) highlight the activities From bottom to Top......upto the assigned calender.

    5- As you Reach the Assigned Calendr, make Right click choose Fill Down.

    you can use same way to add any item.

    best regard

    riad
  4. 0
    Abeer Mahmoud ·
    Thanks for all of you it works.

    Abeer Mohamed Taher
  5. 0
    Syam Mohan ·

    Hi everyone,

    Hi everyone,

                      The Start date and finish date is not matching according to the duration given. calendar assigned is same for all activities. Can anyone tell me the reason for this wrong dates.

  6. 0
    Hamed Najmzadeh ·

    Dear Allhow we can insert new

    Dear All

    how we can insert new project with different calendar in existing project in primavera?

    Sincerely Yours

    H.Najmzadeh

Log in or join to reply