Negative Lag (Here We Go Again) HELP!!!

Benjamin MoraMember for 19 years
Created
1
4
0
I know there have been several threads on the use of negative lag, but I am looking for an alternative. I have to schedule a Red Zone meeting 60 days prior to the completion of certain phases of work.

Now, I know I can, in the initial schedule, setup a relationship with an activity that lands on the date that the meeting supposed to happen, but risk that a delay would push that date out even though it should not delay the meeting.

How can I get around this and not use negative lag with living schedule?

Thanks for your help.

1 reply

Oldest first
  1. 0
    Paul Silver ·
    Benjamin,

    Try applying the primary constraint "as late as possible" to the Meeting Notification activity with FS60 lag to the successor activity, ie. the appropriate Completion Milestone.
    If your completion date moves, (earlier or later) the Meeting Notification activity will move correspondingly.

    Regards

    Paul Silver