Negative Lag (Here We Go Again) HELP!!!
In the Open Standard
Benjamin MoraMember for 19 years
- Created
- 1
- 4
0
I know there have been several threads on the use of negative lag, but I am looking for an alternative. I have to schedule a Red Zone meeting 60 days prior to the completion of certain phases of work.
Now, I know I can, in the initial schedule, setup a relationship with an activity that lands on the date that the meeting supposed to happen, but risk that a delay would push that date out even though it should not delay the meeting.
How can I get around this and not use negative lag with living schedule?
Thanks for your help.
Now, I know I can, in the initial schedule, setup a relationship with an activity that lands on the date that the meeting supposed to happen, but risk that a delay would push that date out even though it should not delay the meeting.
How can I get around this and not use negative lag with living schedule?
Thanks for your help.
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?