Successor with Relationship FS (finish to start)Problem
In the Open Standard
Abeer MahmoudMember for 18 years 4 months
- Created
- 9
- 17
0
Dear all
In P5 If I have an activity ID 44 will start Sep. 10, 2008 and will finish Sep. 12, 2008; this activity has a successor with relationship FS (finish to start) with
Activity ID 55 when I make a schedule command; Activity 55 will start on Sep. 12, 2008 I wonder why it is not start as expected on Sep. 13, 2008.
Can you help me to solve this problem?
Regards,
Abeer Mohamed Taher
In P5 If I have an activity ID 44 will start Sep. 10, 2008 and will finish Sep. 12, 2008; this activity has a successor with relationship FS (finish to start) with
Activity ID 55 when I make a schedule command; Activity 55 will start on Sep. 12, 2008 I wonder why it is not start as expected on Sep. 13, 2008.
Can you help me to solve this problem?
Regards,
Abeer Mohamed Taher
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?