Original Duration on P6

Khalil MasoudMember for 19 years
Created
2
2
0
Hi PP:

in the column of "Original Duration" I can only see zeros and other low figures different from what i originally entered. for example; for a certain activity: the O.D is 1 , but the start and finish dates are August 02 & August 28, respectivaly. Any one can suggest how can i retrieve my original durations??

Thanks

2 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Khalil,

    You can only retrieve your original duration if have already created a Baseline or you have a backup copy to your schedule.


    Arnold
  2. 0
    Dieter Wambach ·
    Hi Khalil
    Open Edit --> User Preferences --> Time Units. Check the entry under Durations Format. I’m doubting that you changed to weeks or to months. Select "Show Duration Label" for both Units and durations.
    Regards
    Dieter