Original Duration on P6
In the Open Standard
Khalil MasoudMember for 19 years
- Created
- 2
- 2
0
Hi PP:
in the column of "Original Duration" I can only see zeros and other low figures different from what i originally entered. for example; for a certain activity: the O.D is 1 , but the start and finish dates are August 02 & August 28, respectivaly. Any one can suggest how can i retrieve my original durations??
Thanks
in the column of "Original Duration" I can only see zeros and other low figures different from what i originally entered. for example; for a certain activity: the O.D is 1 , but the start and finish dates are August 02 & August 28, respectivaly. Any one can suggest how can i retrieve my original durations??
Thanks
2 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?