P6.1 Group Activities
In the Open Standard
Kumar JMember for 25 years 3 months
- Created
- 1
- 1
0
Dear All,
In P6.1 whenever i Open a project, the activities are grouped as per the last opened project Grouping. If the last project was X and if i try to open Y project, the Y project’s activities are grouped as per X project last activity grouping.
In Project Planner P3, whenever we open project the activities are organised as it was the last time i closed the project.
The only solution i could figure out is to save separate layout and open them, after opening the project.
Regards,
Bharath
In P6.1 whenever i Open a project, the activities are grouped as per the last opened project Grouping. If the last project was X and if i try to open Y project, the Y project’s activities are grouped as per X project last activity grouping.
In Project Planner P3, whenever we open project the activities are organised as it was the last time i closed the project.
The only solution i could figure out is to save separate layout and open them, after opening the project.
Regards,
Bharath
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?