Skip to content

P6 dbase backup

Ahmed SeddikMember for 20 years 10 months
Created
5
1
0
I make dbase backup by using SQL Server Management Studio Express , when restore this backup at another pc it fail to open how can I solve this problem

5 replies

Oldest first
  1. 0
    Arnold Puy ·
    Hi Ahmed,

    Did you specify the source & location of backup sets to restore? Make sure that you choose from device instead of from database.
  2. 0
    Dieter Wambach ·
    Ahmed
    I assume this is an item of the SQL-Server. Did you synchronize Privuser and pubuser? Without synchronization SQL-Server doesn’t accept restored data from different servers.
    Regards
    Dieter
  3. 0
    Ahmed Seddik ·
    I need to use the backup at another server
  4. 0
    Duy Huynh ·
    Verify the following after you restored the db into the new server (login to MS SQL management studio first):
    - Are there ’privuser’ and ’pubuser’ created as log in name for the server (under: /Security/Logins)? If no create this two.

    - Next, after the two users above available, make a "New Query" like below:

    exec sp_change_users_login ’Update_One’,’privuser’,’privuser’
    exec sp_change_users_login ’Update_One’,’pubuser’,’pubuser’
    go

    This will update privuser and pubuser of the server into the database.

    Hope this help
  5. 0
    Duy Huynh ·
    Sorry, before that two lines in the query, you need to specify:

    use [pmdb$primavera] -- change it to your actual P6 database name as needed.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?